Stages of Home Building

 

home

 
Lender approval and release of contingencies for start
Apply for building permit
Stake the building
Dig footers
Temporary power hook-up in place
Footer inspection/city
Pour footers
Engineers pin building footing

Masons lay foundation blocks
Foundation inspection/city
Prep crawl area
Install perimeter drains
Frame first floor system walls
Install water and sewer laterals
Frame deck package
Frame second floor system walls

Truss delivery
Crane to set trusses
Frame roof system
Install exterior doors
Prep garage slab
Install windows
Frame exterior trim
install HVAC rough-in

Pour garage slab
Build & install fireplace
Paint exterior (if any)
Install plumbing rough-in
Install electrical rough-in
Install roof finish
Plumbing/flect/HVAC inspection
Install vinyl siding

Masons install face brick
Install batt insulation
Hang and finish drywall
Flat work prep
Install guttering
Pour and finish exterior concrete
Rough grade/yard
Install attic insulation/blown

Install garage door and seed
Install landscaping package
Final grading and see
Install mailbox
Install splash blocks
Prime walls for painting
Switch/plug installation
Install vinyl and ceramic flooring

Install cabinets and tops
Install interior trim
Paint interior of building
Appliance delivery/install
Trim-out/plumbing
Trim-out/electrical
Trim-out HVAC
Install mirrors

Install bath accessories
Install shelving
Install carpets
Install door/cabinet knobs
Cleaning done
Final inspection
Company punch list
Homeowner visit/list
Closing